    Ready to use capsule containing quick-setting, non-chloride, non-shrink cementitious compound.


    Cemextra Grout Capsules

  • Enables easy installation of rockbolts right down its entire length
  • Protects rockbolts from corrosive action of the groundwater or moisture
  • Increases high early strength development
  • Economical method of rockbolting
  • Shockproof


  • Underground excavation support in mining, dam construction, waterways, and roadway tunnels.


    Slope stabilization for roads, bridges, and hill sides.


    Building foundation excavation ground wall support and concrete forms anchorage during concreting.

    The CEMEXTRA Grout Capsules may be used with Rockbolts, Rock Anchors, and Soil Nails made of reinforced steel bar, all-threaded steel bar (Dywydag), and all-threaded glass fiber-reinforced plastic bar (GRP)

    The CEMEXTRA rockbolts may be made with the following coatings:

  • Black Iron
  • Galvanized Iron
  • Epoxy Coating

    Installation of CEMEXTRA Capsules and Rockbolts

    1. Clean the drill hole with wet cloth or sponge attached to a stick.

    2. Soak the capsules in water for 2-3 minutes or until the bubbling stops. After the capsule is soaked in water the compound in resilient and plasticized for a few minutes.

    3. Insert the capsules. If necessary, especially for long holes, Insert the capsules with the aid of a thin-walled plastic or steel pipe. Firmly tamp each capsule with the stick. Put enough capsules until the drill hole is full. Cut the capsule if needed.

    4. Push the rockbolt manually or with a tool such as the rockdrill into the drillhole filled with the capsules. Its pointed end will rupture the capsule and displace the compound at the same time pushing it against the walls and cracks of the drillhole. The excess compound will spill out of the hole.

    5. Install the bearing plate and nut. Tighten the nut after 2-hours or more.